PolyLEVEL Alberta Corp. Case Studies: Sunnybrook Sub-Station Genesee Plant Warehouse Slab
Wednesday, August 5th, 2015 by Michel Belanger
View Photo Gallery
Challenge
A nearby excavation caused a warehouse slab to sink. The warehouse slab was 11" thick in the middle with thicker 18" to 24" thick concrete at the perimeter. The corner of the warehouse sank approximately 3 inches affecting an area 30 feet X 30 feet.
Solution
Our crew used PolyLEVEL Commercial Formula PL400 to lift the slab back to grade with excellent results.